Skip to the engineering article

Engineering Insights

ANSI Pump RFQ & Commissioning Checklist: From Quote to Field Startup

Five practical checks help buyers move from ANSI pump RFQ to commissioning: define the operating profile, verify the system curve and NPSH, compare supplier evidence, and separate factory testing from field acceptance.

Engineer evaluating ANSI pump RFQ and commissioning in an industrial pump system
Engineering source review Replacement-data workflow Updated Nov 25, 2026
RFQ ownership

Start With the Handover, Not Just the Pump Model

A useful ANSI pump RFQ does more than identify a pump and duty point. It should carry the same engineering basis from quotation through technical approval, factory testing, shipment release, installation and field startup. If requirements disappear between those stages, the project can pass a factory check and still fail at site—or arrive on site with unresolved assumptions that were never priced or documented.

RFQ-to-Commissioning Decision Chain

Each stage should inherit the approved duty, interfaces, materials, test scope and outstanding deviations from the stage before it.

01

RFQ inputs

Duty envelope, liquid, interfaces, material, seal, driver and document requirements.

02

Technical bid

Proposed model, curve, assumptions, deviations, tests and evidence.

03

Approved package

Controlled drawings, agreed datasheet, test/inspection scope and release conditions.

04

FAT / shipment

Verify the purchased test scope and close document/deviation gates before release.

05

Site startup

Verify installation readiness, pre-start conditions and operating baseline.

The RFQ should create a traceable handover record, not a one-time quotation worksheet.

Page boundary

This guide focuses on the handover from RFQ to commissioning. Detailed pump-curve interpretation, NPSH calculations, material selection and B73.1 dimensional interchangeability are handled in the linked specialist guides rather than repeated here.

01 / Operating envelope

Define Normal, Minimum and Maximum Duty Before Suppliers Quote

A single “design point” can hide the conditions that actually govern reliability, NPSH, motor load and control behavior. Record the credible operating states and identify whether each value is measured, calculated or estimated.

Condition Flow Head / pressure basis Temperature Hours / cycle Control mode
Normal [value + unit] [value + unit] [value + unit] [hours / cycle] Valve / VFD / fixed speed
Minimum [value + unit] [value + unit] [value + unit] [hours / cycle] [condition]
Maximum [value + unit] [value + unit] [value + unit] [hours / cycle] [condition]
Process stateBatch, seasonal, parallel-pump, tank-level or control-valve conditions that move the duty.
Evidence levelMark each input as measured, calculated, estimated or assumed.
Selection consequenceTell suppliers which conditions are continuous, occasional, startup-only or upset cases.
02 / Hydraulic evidence

Put the Curve, System Condition and NPSH Basis Into the RFQ

The RFQ does not need to become a pump-curve textbook. It does need enough evidence for every supplier to evaluate the same operating range. Ask for the offered curve with pump size, speed, impeller diameter, efficiency, power and NPSHr basis identified, and compare it with the project system condition.

Operating-Envelope Review

Use normal, minimum and maximum system conditions to review where the proposed pump will actually operate.

01

System data

Elevation, vessel pressure, piping losses, valves, exchangers and control state.

02

Pump curve

Flow/head curve at the quoted speed and impeller configuration.

03

Operating region

Verify manufacturer / applicable ANSI-HI POR and AOR limits for this pump.

04

NPSH

Compare project NPSHa with manufacturer NPSHr across the credible range.

05

Decision

Accept, resize, trim, change speed/control strategy or review the system.

Do not publish one universal POR/AOR percentage for every rotodynamic pump. Use the applicable pump/manufacturer/ANSI-HI operating-region basis.

For the detailed method, use the centrifugal pump curve guide, the NPSH and operating-region guide, and the pump calculators.

03 / Technical bid comparison

Normalize Supplier Evidence Before Comparing Purchase Price

Price becomes useful only after the technical scope is normalized. Ask every supplier to return the same evidence fields and identify deviations explicitly. Missing evidence should remain visible as an open technical item rather than being treated as equivalent compliance.

Evidence / return item RFQ requirement Supplier A Supplier B Supplier C
Exact model / configuration [required basis] [response] [response] [response]
Curve, speed, impeller and duty [required basis] [attach] [attach] [attach]
Motor / power margin [required basis] [response] [response] [response]
Material specification [grade / component scope] [response] [response] [response]
Seal / containment arrangement [required basis] [response] [response] [response]
GA / installation interfaces [drawing required] [attach] [attach] [attach]
FAT / hydrotest / inspection [scope / standard] [scope] [scope] [scope]
Documentation / traceability [required list] [list] [list] [list]
Deviation list Required [open/closed] [open/closed] [open/closed]
Lead time / commercial assumptions [basis] [response] [response] [response]

Evidence is project-defined

MTR, PMI, NDE, balance reports and certified test reports should be requested when the RFQ, ITP, material risk or project specification requires them. Do not present every document as a universal requirement for every ANSI pump order.

04 / Purchase-order test scope

Define FAT and Inspection Before Technical Release

If a factory acceptance test or inspection package is important to the project, define it before the purchase order is released. “Tested” is not an acceptance criterion. State the governing test basis, guarantee point, required test scope, documentation, calibration evidence and any witness or hold points.

Performance testStandard/edition, guarantee point, acceptance basis and report fields.
NPSH testRequired or not required; define the purchased basis rather than assuming it is included.
Hydrostatic testApplicable pressure-boundary procedure, acceptance criterion and report evidence.
Inspection / NDEType, component scope, extent and acceptance basis if specified.
Witness / hold pointsParty, notice period, release authority and documentation.
Final document packageApproved drawings, reports, certificates, deviation status and IOM/manuals.

For hydraulic test planning, use the ANSI/HI 14.6 acceptance test guide. For casing pressure-boundary evidence, use the pump casing hydrostatic testing guide.

05 / Handover boundary

Factory Acceptance Testing Is Not Field Commissioning

A factory test verifies the supplied pump under a defined test setup. Field commissioning verifies the installed pump in the actual piping, suction system, driver, controls and process. Both are important, but they answer different engineering questions.

Question Factory Acceptance Test Field Commissioning
Location Factory / test stand Installed system
Main purpose Verify purchased test/acceptance requirement Verify installed-system readiness and operating baseline
Hydraulic environment Controlled test setup and specified test fluid Actual piping, suction conditions, process/control state
Alignment / piping strain Not representative of final installed piping Site installation condition must be verified
Vibration Defined factory configuration if purchased Installed baseline under stable operating conditions
Deliverable Factory test / inspection report Startup and baseline record

Decision rule

A failed field result does not automatically invalidate the FAT, and a passed FAT does not prove the installed system is correct. Investigate the evidence chain before assigning cause.

06 / Site Gate 1

Installation Readiness: Is the Pump Mechanically Ready to Start?

Before startup, verify that the installed condition matches the approved equipment and manufacturer/project procedure. This gate intentionally avoids one universal alignment, pipe-strain or temperature limit because acceptance values depend on the pump, coupling, driver, thermal growth, installation and governing procedure.

Foundation / baseAnchor, grout/base condition and support released for service.
PipingSupported independently; no forced fit at pump nozzles; system cleanliness addressed.
Final alignmentChecked after installation/piping using the applicable coupling/OEM/project procedure.
Coupling / guardCorrect assembly, spacer condition where applicable and guarding ready.
Seal systemFlush, barrier, quench or support system connected, clean and ready as applicable.
LubricationCorrect lubricant, fill method and level per the equipment IOM.
InstrumentationRequired pressure, flow, temperature, speed, power and vibration measurement points ready.
Suction conditionSystem clean, priming/venting provisions ready and credible suction condition available.
Electrical / controlsMotor, protection, permissives, interlocks and control logic released.
07 / Site Gate 2

Pre-Start Verification: Confirm Rotation, Priming and Support Systems

Use the exact manufacturer IOM and approved startup procedure for the installed pump. OEM manuals commonly require checks such as rotation verification, correct priming, lubrication and coupling/guard readiness, but the sequence and limits are configuration-specific.

Pre-Start Gate

Do not start until every applicable prerequisite is either confirmed or formally dispositioned.

01

Rotation

Verify driver rotation using the applicable safe uncoupled/jog procedure.

02

Free rotation

Confirm rotor turns freely where the IOM/procedure calls for a hand-rotation check.

03

Prime / vent

Fill/vent the pump and suction path as required for the pump/system configuration.

04

Auxiliaries

Put seal support, cooling, lubrication and instrumentation into the required state.

05

Valve / control state

Use the approved pump/system startup procedure—do not apply one generic valve sequence to every pump.

No universal startup sequence

Do not convert a single OEM procedure into a blanket instruction for all ANSI process pumps. Self-priming, low-flow, special control, minimum-flow and process-system arrangements can require different startup logic.

08 / Site Gate 3

Controlled Startup: Establish a Traceable Operating Baseline

Once the pump is operating in a stable, approved condition, record enough data to compare the installed result with the approved duty and to create a maintenance baseline. Use the project, manufacturer and applicable standards for acceptance limits rather than inserting generic “green-zone” values.

Parameter Measured value Expected / criterion Instrument / source Status
Flow ___ Approved duty / operating range Flow meter / process measurement PASS / HOLD
Suction pressure ___ Project/system basis Gauge / transmitter PASS / HOLD
Discharge pressure ___ Project/system basis Gauge / transmitter PASS / HOLD
Pump head / differential ___ Curve / approved duty comparison Calculated from field data PASS / HOLD
Speed ___ Approved speed / VFD state Tachometer / VFD PASS / HOLD
Motor current / input ___ Motor / project / operating basis MCC / VFD / meter PASS / HOLD
Vibration ___ Project / OEM / applicable HI or ISO basis Defined measurement points PASS / HOLD
Bearing housing temperature ___ OEM / project criterion and trend Sensor / handheld instrument PASS / HOLD
Seal / leakage condition ___ Seal/IOM/project basis Inspection / instruments PASS / HOLD
Process temperature / state ___ Recorded actual duty Process instrument PASS / HOLD

Keep the first stable data set

The startup record becomes far more valuable when the measurement locations, instrument/source and operating condition are preserved. That makes later vibration, temperature and hydraulic trends comparable to a known baseline.

Mark 3 high silicon iron commissioning record

For the Group 2 high silicon iron configuration, attach the installed nameplate and applicable IOM revision to the site handover. Use the following fields to capture the evidence for the actual pump and site startup procedure.

  • Pump identity: complete size, serial number, impeller type and actual trim, seal or packing arrangement, and drawing revision.
  • Installation: record pipe support and alignment before and after piping is connected. Record the hot alignment check when specified, with the unit safely stopped under the site procedure. Confirm the applicable nozzle load requirements before release.
  • Pre-start: record the installed lubrication method, oil level indication or grease specification, rotation check, priming status, and the verified seal or packing support connections.
  • First stable run: log duty, speed, suction and discharge pressure, flow, driver load, vibration, bearing temperature and seal observations. Record the measurement locations and fluid temperature for later comparison.

Read the high silicon iron nameplate example · See the bearing record fields

Source: Flowserve Mark 3 High Silicon Iron Pumps IOM, PCN 71569249 (09-04), §§4.6, 4.8 and 5.1–5.10, pp. 16–26.

09 / Release control

Do Not Release the PO or Shipment With Critical Gaps Still Open

PO technical release Shipment / site release
Duty envelope and offered model/configuration agreed Approved GA/drawings at final controlled revision
Curve, speed, impeller and motor basis agreed Purchased FAT / hydrotest / inspection evidence complete
Material and seal/containment scope agreed Material/traceability evidence complete where required
Installation interfaces reviewed IOM, preservation, packing and final document index complete
Inspection/test/document requirements defined Open deviations closed or formally accepted
10 / Lifecycle record

Build One RFQ-to-Commissioning Handover Record

The most useful project record links the original requirement to the supplier response, factory evidence and startup baseline. This reduces the chance that field teams receive equipment without knowing the assumptions that governed selection and acceptance.

IdentityTag, manufacturer, model, size, serial and controlled drawing revision.
DutyNormal/min/max flow, head, speed, liquid and control state.
InterfacesNozzles, base/foundation, shaft/coupling, driver and service clearance.
Materials / sealExact approved component materials and containment arrangement.
Factory evidencePurchased test/inspection results, documents and deviations.
Site baselineStartup condition, measured hydraulic/electrical/mechanical values and release status.
11 / Copy-paste checklist

ANSI Pump RFQ and Commissioning Handover Checklist

Existing equipmentManufacturer, model, size, frame/group, tag, serial and nameplate.
Requested scopeComplete pump or approved replacement components such as casing, cover, impeller, shaft, or selected metallic mechanical-seal components.
Operating profileNormal, minimum and maximum flow/head plus hours/cycle and control state.
LiquidChemistry, concentration, SG/density, viscosity, vapor pressure, solids, gas and contaminants where relevant.
Temperature / suctionOperating/design temperature and NPSHa/suction vessel level/pressure basis where available.
DriverVoltage, frequency, power, speed, enclosure, VFD range and project requirements.
Seal / containmentSeal chamber, seal arrangement, faces/elastomers and flush/barrier/support requirements.
MaterialsExact material grades by component and any lining/coating requirements.
Installation interfacesGA, flange/nozzle, base/foundation, shaft/coupling and envelope constraints.
Factory acceptancePerformance/NPSH/hydrotest/inspection scope, criteria, reports and witness/hold points.
DocumentsDrawings, curve, datasheet, required MTR/PMI/NDE/traceability, deviations and IOM.
CommissioningInstallation readiness, pre-start procedure, measurement plan and baseline record.

Use the official B73 data sheet when it fits the project

ASME provides a fillable B73 pump data sheet for specification, purchase packages and existing-equipment documentation. Use it as the core equipment datasheet where appropriate, then add project-specific FAT, document and commissioning handover requirements.

ISO pump RFQ checklist — the 6 items to send

12 / Tools and next-step resources

Use Specialist Tools Instead of Repeating Every Calculation in the RFQ

For a workbook-based hydraulic record, review the pump system hydraulic calculation spreadsheet. Its guide explains the inputs, pressure-loss calculation, pump head, power and NPSH outputs so the calculation basis can travel with the RFQ.

ANSI Pump Selection & ReplacementUse the worksheet when model, duty or supporting evidence is incomplete.
Pump CalculatorsOrganize TDH, friction, NPSH, power and related hydraulic inputs.
ASME B73.1 GuideSeparate standardized installation interfaces from model-specific internal compatibility.
ANSI/HI 14.6 GuideDefine purchased performance/NPSH/hydrostatic acceptance-test scope.
Hydrostatic Test GuideReview casing pressure-boundary test evidence and report validity.
NPSH / POR / AOR GuideReview suction margin and operating-region decisions in depth.
13 / Frequently asked questions

ANSI Pump RFQ and Commissioning FAQ

What should an ANSI pump RFQ include?

Include the existing equipment identity, normal/minimum/maximum duty, liquid and temperature data, suction/NPSH information, exact materials, seal/containment requirements, driver information, installation interfaces, factory test/inspection scope, document requirements, deviations and the expected field-commissioning handover.

What is the difference between FAT and pump commissioning?

FAT verifies the purchased pump under a defined factory test configuration. Commissioning verifies the installed pump and system, including final installation, piping, driver, controls, suction condition and stable operating baseline.

Does ASME B73.1 define one universal commissioning alignment tolerance?

No universal site alignment value should be taken from this article. Use the applicable pump IOM, coupling procedure, project specification and thermal-growth/alignment requirements for the installed configuration.

Should POR always be 70% to 120% of BEP?

No. Preferred and allowable operating regions depend on pump type, specific speed, manufacturer design and the applicable ANSI/HI guidance. Ask for the operating-region limits for the actual proposed pump rather than applying one fixed percentage to every pump.

What should be recorded during startup?

Record the stable operating condition and the measurements needed to compare field performance with the approved duty, such as flow, suction/discharge pressure, speed, motor input/current, vibration, bearing-housing temperature, seal condition and relevant process state.

Does a passed factory performance test guarantee field performance?

No. A passed factory test confirms the purchased factory acceptance requirement. Field performance also depends on the installed system, piping, suction condition, controls, alignment, process liquid and operating state.

14 / Technical references

Technical Sources

  1. ASME — B73.1-2026, Specification for Horizontal End Suction Centrifugal Pumps for Chemical Process
  2. Hydraulic Institute — ANSI/HI 14.6 Rotodynamic Pumps for Hydraulic Performance Acceptance Tests
  3. Hydraulic Institute — ANSI/HI 9.6.3 Rotodynamic Pumps Guideline for Operating Regions
  4. Hydraulic Institute — ANSI/HI 9.6.4 Rotodynamic Pumps for Vibration Measurements and Allowable Values
  5. ITT Goulds Pumps — NM 3196 i-FRAME Installation, Operation and Maintenance Manual
  6. Flowserve — Durco Mark 3 Sealed ASME (ANSI) Chemical Process Pump

Engineering Review

Send the pump model, operating duty and available process data before selecting or replacing wetted components.

Request Engineering Review
Quick Quote