Start With the Handover, Not Just the Pump Model
A useful ANSI pump RFQ does more than identify a pump and duty point. It should carry the same engineering basis from quotation through technical approval, factory testing, shipment release, installation and field startup. If requirements disappear between those stages, the project can pass a factory check and still fail at site—or arrive on site with unresolved assumptions that were never priced or documented.
RFQ-to-Commissioning Decision Chain
Each stage should inherit the approved duty, interfaces, materials, test scope and outstanding deviations from the stage before it.
RFQ inputs
Duty envelope, liquid, interfaces, material, seal, driver and document requirements.
Technical bid
Proposed model, curve, assumptions, deviations, tests and evidence.
Approved package
Controlled drawings, agreed datasheet, test/inspection scope and release conditions.
FAT / shipment
Verify the purchased test scope and close document/deviation gates before release.
Site startup
Verify installation readiness, pre-start conditions and operating baseline.
Page boundary
This guide focuses on the handover from RFQ to commissioning. Detailed pump-curve interpretation, NPSH calculations, material selection and B73.1 dimensional interchangeability are handled in the linked specialist guides rather than repeated here.
Define Normal, Minimum and Maximum Duty Before Suppliers Quote
A single “design point” can hide the conditions that actually govern reliability, NPSH, motor load and control behavior. Record the credible operating states and identify whether each value is measured, calculated or estimated.
| Condition | Flow | Head / pressure basis | Temperature | Hours / cycle | Control mode |
|---|---|---|---|---|---|
| Normal | [value + unit] | [value + unit] | [value + unit] | [hours / cycle] | Valve / VFD / fixed speed |
| Minimum | [value + unit] | [value + unit] | [value + unit] | [hours / cycle] | [condition] |
| Maximum | [value + unit] | [value + unit] | [value + unit] | [hours / cycle] | [condition] |
Put the Curve, System Condition and NPSH Basis Into the RFQ
The RFQ does not need to become a pump-curve textbook. It does need enough evidence for every supplier to evaluate the same operating range. Ask for the offered curve with pump size, speed, impeller diameter, efficiency, power and NPSHr basis identified, and compare it with the project system condition.
Operating-Envelope Review
Use normal, minimum and maximum system conditions to review where the proposed pump will actually operate.
System data
Elevation, vessel pressure, piping losses, valves, exchangers and control state.
Pump curve
Flow/head curve at the quoted speed and impeller configuration.
Operating region
Verify manufacturer / applicable ANSI-HI POR and AOR limits for this pump.
NPSH
Compare project NPSHa with manufacturer NPSHr across the credible range.
Decision
Accept, resize, trim, change speed/control strategy or review the system.
For the detailed method, use the centrifugal pump curve guide, the NPSH and operating-region guide, and the pump calculators.
Normalize Supplier Evidence Before Comparing Purchase Price
Price becomes useful only after the technical scope is normalized. Ask every supplier to return the same evidence fields and identify deviations explicitly. Missing evidence should remain visible as an open technical item rather than being treated as equivalent compliance.
| Evidence / return item | RFQ requirement | Supplier A | Supplier B | Supplier C |
|---|---|---|---|---|
| Exact model / configuration | [required basis] | [response] | [response] | [response] |
| Curve, speed, impeller and duty | [required basis] | [attach] | [attach] | [attach] |
| Motor / power margin | [required basis] | [response] | [response] | [response] |
| Material specification | [grade / component scope] | [response] | [response] | [response] |
| Seal / containment arrangement | [required basis] | [response] | [response] | [response] |
| GA / installation interfaces | [drawing required] | [attach] | [attach] | [attach] |
| FAT / hydrotest / inspection | [scope / standard] | [scope] | [scope] | [scope] |
| Documentation / traceability | [required list] | [list] | [list] | [list] |
| Deviation list | Required | [open/closed] | [open/closed] | [open/closed] |
| Lead time / commercial assumptions | [basis] | [response] | [response] | [response] |
Evidence is project-defined
MTR, PMI, NDE, balance reports and certified test reports should be requested when the RFQ, ITP, material risk or project specification requires them. Do not present every document as a universal requirement for every ANSI pump order.
Define FAT and Inspection Before Technical Release
If a factory acceptance test or inspection package is important to the project, define it before the purchase order is released. “Tested” is not an acceptance criterion. State the governing test basis, guarantee point, required test scope, documentation, calibration evidence and any witness or hold points.
For hydraulic test planning, use the ANSI/HI 14.6 acceptance test guide. For casing pressure-boundary evidence, use the pump casing hydrostatic testing guide.
Factory Acceptance Testing Is Not Field Commissioning
A factory test verifies the supplied pump under a defined test setup. Field commissioning verifies the installed pump in the actual piping, suction system, driver, controls and process. Both are important, but they answer different engineering questions.
| Question | Factory Acceptance Test | Field Commissioning |
|---|---|---|
| Location | Factory / test stand | Installed system |
| Main purpose | Verify purchased test/acceptance requirement | Verify installed-system readiness and operating baseline |
| Hydraulic environment | Controlled test setup and specified test fluid | Actual piping, suction conditions, process/control state |
| Alignment / piping strain | Not representative of final installed piping | Site installation condition must be verified |
| Vibration | Defined factory configuration if purchased | Installed baseline under stable operating conditions |
| Deliverable | Factory test / inspection report | Startup and baseline record |
Decision rule
A failed field result does not automatically invalidate the FAT, and a passed FAT does not prove the installed system is correct. Investigate the evidence chain before assigning cause.
Installation Readiness: Is the Pump Mechanically Ready to Start?
Before startup, verify that the installed condition matches the approved equipment and manufacturer/project procedure. This gate intentionally avoids one universal alignment, pipe-strain or temperature limit because acceptance values depend on the pump, coupling, driver, thermal growth, installation and governing procedure.
Pre-Start Verification: Confirm Rotation, Priming and Support Systems
Use the exact manufacturer IOM and approved startup procedure for the installed pump. OEM manuals commonly require checks such as rotation verification, correct priming, lubrication and coupling/guard readiness, but the sequence and limits are configuration-specific.
Pre-Start Gate
Do not start until every applicable prerequisite is either confirmed or formally dispositioned.
Rotation
Verify driver rotation using the applicable safe uncoupled/jog procedure.
Free rotation
Confirm rotor turns freely where the IOM/procedure calls for a hand-rotation check.
Prime / vent
Fill/vent the pump and suction path as required for the pump/system configuration.
Auxiliaries
Put seal support, cooling, lubrication and instrumentation into the required state.
Valve / control state
Use the approved pump/system startup procedure—do not apply one generic valve sequence to every pump.
No universal startup sequence
Do not convert a single OEM procedure into a blanket instruction for all ANSI process pumps. Self-priming, low-flow, special control, minimum-flow and process-system arrangements can require different startup logic.
Controlled Startup: Establish a Traceable Operating Baseline
Once the pump is operating in a stable, approved condition, record enough data to compare the installed result with the approved duty and to create a maintenance baseline. Use the project, manufacturer and applicable standards for acceptance limits rather than inserting generic “green-zone” values.
| Parameter | Measured value | Expected / criterion | Instrument / source | Status |
|---|---|---|---|---|
| Flow | ___ | Approved duty / operating range | Flow meter / process measurement | PASS / HOLD |
| Suction pressure | ___ | Project/system basis | Gauge / transmitter | PASS / HOLD |
| Discharge pressure | ___ | Project/system basis | Gauge / transmitter | PASS / HOLD |
| Pump head / differential | ___ | Curve / approved duty comparison | Calculated from field data | PASS / HOLD |
| Speed | ___ | Approved speed / VFD state | Tachometer / VFD | PASS / HOLD |
| Motor current / input | ___ | Motor / project / operating basis | MCC / VFD / meter | PASS / HOLD |
| Vibration | ___ | Project / OEM / applicable HI or ISO basis | Defined measurement points | PASS / HOLD |
| Bearing housing temperature | ___ | OEM / project criterion and trend | Sensor / handheld instrument | PASS / HOLD |
| Seal / leakage condition | ___ | Seal/IOM/project basis | Inspection / instruments | PASS / HOLD |
| Process temperature / state | ___ | Recorded actual duty | Process instrument | PASS / HOLD |
Keep the first stable data set
The startup record becomes far more valuable when the measurement locations, instrument/source and operating condition are preserved. That makes later vibration, temperature and hydraulic trends comparable to a known baseline.
Mark 3 high silicon iron commissioning record
For the Group 2 high silicon iron configuration, attach the installed nameplate and applicable IOM revision to the site handover. Use the following fields to capture the evidence for the actual pump and site startup procedure.
- Pump identity: complete size, serial number, impeller type and actual trim, seal or packing arrangement, and drawing revision.
- Installation: record pipe support and alignment before and after piping is connected. Record the hot alignment check when specified, with the unit safely stopped under the site procedure. Confirm the applicable nozzle load requirements before release.
- Pre-start: record the installed lubrication method, oil level indication or grease specification, rotation check, priming status, and the verified seal or packing support connections.
- First stable run: log duty, speed, suction and discharge pressure, flow, driver load, vibration, bearing temperature and seal observations. Record the measurement locations and fluid temperature for later comparison.
Read the high silicon iron nameplate example · See the bearing record fields
Source: Flowserve Mark 3 High Silicon Iron Pumps IOM, PCN 71569249 (09-04), §§4.6, 4.8 and 5.1–5.10, pp. 16–26.
Do Not Release the PO or Shipment With Critical Gaps Still Open
| PO technical release | Shipment / site release |
|---|---|
| Duty envelope and offered model/configuration agreed | Approved GA/drawings at final controlled revision |
| Curve, speed, impeller and motor basis agreed | Purchased FAT / hydrotest / inspection evidence complete |
| Material and seal/containment scope agreed | Material/traceability evidence complete where required |
| Installation interfaces reviewed | IOM, preservation, packing and final document index complete |
| Inspection/test/document requirements defined | Open deviations closed or formally accepted |
Build One RFQ-to-Commissioning Handover Record
The most useful project record links the original requirement to the supplier response, factory evidence and startup baseline. This reduces the chance that field teams receive equipment without knowing the assumptions that governed selection and acceptance.
ANSI Pump RFQ and Commissioning Handover Checklist
Use the official B73 data sheet when it fits the project
ASME provides a fillable B73 pump data sheet for specification, purchase packages and existing-equipment documentation. Use it as the core equipment datasheet where appropriate, then add project-specific FAT, document and commissioning handover requirements.
Use Specialist Tools Instead of Repeating Every Calculation in the RFQ
For a workbook-based hydraulic record, review the pump system hydraulic calculation spreadsheet. Its guide explains the inputs, pressure-loss calculation, pump head, power and NPSH outputs so the calculation basis can travel with the RFQ.
ANSI Pump RFQ and Commissioning FAQ
What should an ANSI pump RFQ include?
Include the existing equipment identity, normal/minimum/maximum duty, liquid and temperature data, suction/NPSH information, exact materials, seal/containment requirements, driver information, installation interfaces, factory test/inspection scope, document requirements, deviations and the expected field-commissioning handover.
What is the difference between FAT and pump commissioning?
FAT verifies the purchased pump under a defined factory test configuration. Commissioning verifies the installed pump and system, including final installation, piping, driver, controls, suction condition and stable operating baseline.
Does ASME B73.1 define one universal commissioning alignment tolerance?
No universal site alignment value should be taken from this article. Use the applicable pump IOM, coupling procedure, project specification and thermal-growth/alignment requirements for the installed configuration.
Should POR always be 70% to 120% of BEP?
No. Preferred and allowable operating regions depend on pump type, specific speed, manufacturer design and the applicable ANSI/HI guidance. Ask for the operating-region limits for the actual proposed pump rather than applying one fixed percentage to every pump.
What should be recorded during startup?
Record the stable operating condition and the measurements needed to compare field performance with the approved duty, such as flow, suction/discharge pressure, speed, motor input/current, vibration, bearing-housing temperature, seal condition and relevant process state.
Does a passed factory performance test guarantee field performance?
No. A passed factory test confirms the purchased factory acceptance requirement. Field performance also depends on the installed system, piping, suction condition, controls, alignment, process liquid and operating state.
Technical Sources
- ASME — B73.1-2026, Specification for Horizontal End Suction Centrifugal Pumps for Chemical Process
- Hydraulic Institute — ANSI/HI 14.6 Rotodynamic Pumps for Hydraulic Performance Acceptance Tests
- Hydraulic Institute — ANSI/HI 9.6.3 Rotodynamic Pumps Guideline for Operating Regions
- Hydraulic Institute — ANSI/HI 9.6.4 Rotodynamic Pumps for Vibration Measurements and Allowable Values
- ITT Goulds Pumps — NM 3196 i-FRAME Installation, Operation and Maintenance Manual
- Flowserve — Durco Mark 3 Sealed ASME (ANSI) Chemical Process Pump
